PROJECT OVERVIEW

Simpson Coulson was appointed as Principal Contractor under an NEC3 contract. We were able to deliver a major programme of design, engineering and construction works for PD Ports at Cargo Fleet Wharf, Teesside.

The development centres on a purpose-built conservancy facility providing approximately 22,000sqft of combined workshop, storage and office accommodation. Designed to support PD Ports’ marine operations, the facility incorporates a substantial structural steel frame. Also featuring two internal mezzanine levels, a 5-tonne overhead travelling crane and specialist access arrangements for vessel maintenance.

2 interior
23130 pdp cfw3

WIDER SCOPE

Beyond the design and construction of the building itself, Simpson Coulson’s scope encompasses an extensive programme of associated marine and civil engineering works. This enhances the surrounding wharf infrastructure to accommodate operational vessels, improve berthing arrangements and support long term conservancy activities.

EXPERTISE

With the principal building complete and associated infrastructure works progressing, the project demonstrates Simpson Coulson’s capability to integrate structural design, specialist fabrication, civil engineering and marine construction within a coordinated, multidisciplinary delivery programme.

22,000 sq ft

Specialist office and workshop facility

5T

Overhead travelling crane installation

18,000L

Marine refuelling station

NEC3

Main contractor

ENGINEERING CHALLENGE

The development needed to accommodate PD Ports’ diverse conservancy fleet, combining a purpose-built 22,000sqft workshop and office facility with dedicated vessel maintenance, berthing, refuelling and servicing infrastructure.

Alongside the building construction, significant modifications to the existing wharf were required. This was to support dredgers and operational vessels, including the Tees Guardian. This involved new marine fender systems, specialist access structures, piled foundations and a floating pontoon designed to accommodate changing tidal conditions.

The project presented several interconnected engineering and construction challenges:

Integrating crane systems, office space and specialist workshop
Coordinating activities within an operational port environment
Accommodating various vessel sizes and berthing requirements
Managing piling and foundation works in tidal conditions
Designing floating pontoon access for fluctuating water levels
Undertaking heavy lifting and specialist steelwork installations
Coordinating multiple disciplines under NEC3 contract
whatsapp image 2025 10 07 at 12.43.21 pm (1)

SCOPE OF WORKS

Simpson Coulson’s programme encompasses the design, fabrication, construction and coordination of a comprehensive range of civil, structural, marine and industrial infrastructure works.

Building & Structural Engineering

• Construction of the new conservancy workshop and offices
• Structural steel frame and supporting foundations
• Two internal mezzanine floors
• 5-tonne overhead crane install
• External cladding, glazing, balconies, roller shutter doors
• Internal and external staircases
• Building drainage and services

Marine & Waterfront Engineering

• Removal of existing marine fender structures
• Design, fabrication and installation of replacement fender
• Bespoke steelwork and personnel access arrangements
• Floating pontoon infrastructure design extending 75 metres
• Piled bankseat foundations and pontoon access walkway

Civil Engineering & Infrastructure

• Site preparation, foundations, concrete works and drainage
• Marine bollards, protection plates and associated wharf infrastructure
• Rail and winch foundations
• Marine refuelling station with 18,000 litre storage tank
• External surfacing, access and supporting infrastructure

Project Management

• Contracted NEC3 responsibilities
• Planning, programming and coordination of construction
• Management of specialist subcontractors and suppliers
• Site supervision, health and safety management
• Construction sequencing within operational port environment
• Completion and demobilisation

PROJECT OUTCOME

Award-Winning Marine Facility

Recognised with the Port Development Award at the British Ports Association Annual Conference 2026, the complete Cargo Fleet Wharf Conservancy Facility represents a significant investment in the future of Teesside’s marine infrastructure. This strengthens PD Ports’ capabilities as Statutory Harbour Authority for the River Tees.

With the principal building substantially complete, the facility integrates maintenance, storage and administrative functions within a single operational hub.

23130 pdp cfw2
mezzanine 2
whatsapp image 2025 11 04 at 10.44.06 am (1)
balconies
mezzanine
whatsapp image 2025 10 07 at 12.43.21 pm (1)
whatsapp image 2025 11 04 at 10.44.06 am (4)

TO COMPLETION

INFRASTRUCTURE BUILT FOR THE FUTURE

Simpson Coulson successfully delivered a major new Conservancy Facility at Cargo Fleet Wharf, bringing together civil, structural and marine engineering expertise to create a purpose-built operational hub for PD Ports.

From structural steelwork and specialist construction to modern office accommodation and marine maintenance facilities, this development stands as a flagship example of Simpson Coulson’s multidisciplinary capabilities and our contribution to the continued development of critical port infrastructure in Teesside.

A landmark addition to Teesside’s waterfront infrastructure, showcasing Simpson Coulson’s commitment to engineering excellence and the continued investment in the region’s industrial future.